Who Pays for the AI Power Buildout?
What Virginia, Ohio, and Georgia’s public records say about who carries the risk when a data center reserves power and then pulls out.
A minimum bill is not a cancellation payment.
A data center can use less power than it contracted for, cancel before energization, or leave after service starts. Those are three different events. To know who pays, you have to read the provision that applies at that stage.
Compare the protections.
| Question | Dominion Virginia | AEP Ohio | Georgia Power |
|---|---|---|---|
| Coverage and status | Dominion’s large-load GS-5 class. Virginia SCC identifies a 25 MW demand threshold. Approved; effective January 1, 2027. Eligibility has additional conditions. | AEP Ohio Schedule DCT. Settlement adopted July 9, 2025; tariff became effective July 23, 2025. This isn’t a statewide retail rate. | Georgia Power, PSC docket 44280. The August 2026 commitment is a joint filing for approved large-load data center contracts, not a blanket statewide tariff. |
| Low usage after service starts | For covered customers, separate minimum-demand bases of 85% for transmission and distribution and 60% for generation, subject to tariff provisions. | A tiered contract-capacity floor and a separate prior-billing-demand provision. The utility describes the actual formula, not a universal flat 85% minimum. | The PSC describes minimum billing and longer terms for eligible large loads. The joint filing distinguishes the minimum-bill design from early-termination treatment. |
| Project canceled before energization | Minimum demand percentages do not establish a pre-service cancellation charge. Check the signed facilities or service agreement and the applicable rules. | Under AEP Ohio’s letter of agreement, a qualifying cancellation or delay of more than 12 months before the target energization date can require reimbursement of 100% of covered buildout costs. | Do not assume the joint filing answers every pre-service cancellation question. Check whether a covered contract was approved, and which termination terms actually apply. |
| What remains after an early exit? | The SCC describes a minimum 14-year service obligation for eligible new contracts and credit support for certain customers, but those provisions do not quantify every shared cost. | The utility identifies separate provisions for exiting the service agreement. Reimbursement under the pre-energization letter is not a promise about all residual system costs. | Georgia Power agreed not to seek a defined incremental revenue deficiency from non-large-load customers during the remaining term after early termination of a covered contract. Recovery of unmitigated costs remains for the commission to determine. |
Sources: Virginia SCC order summary · Virginia SCC large-load provisions · AEP Ohio Schedule DCT explanation · Georgia PSC joint filing · Georgia PSC fact sheet.
A 100 MW project reserves power, then cancels.
Assume the utility has spent money on project-specific infrastructure and the developer cancels before service. Ohio’s published letter-of-agreement explanation gives a direct example of covered buildout reimbursement. Virginia’s minimum bills alone do not tell you what is due for that cancellation. Georgia’s joint filing addresses a defined shortfall after early termination of a covered approved contract. Whether that filing reaches the hypothetical depends on the contract and its status.
What remains unknown: the net cost after payments, avoided spending, and replacement demand, and how any uncovered shared investment would be allocated.
What the Virginia percentages mean.
The two illustrative floors are 85 MW for transmission and distribution and 60 MW for generation. They are separate billing-demand bases, not additive amounts, an exit payment, or a retail bill.
What changed, and when.
Tracked milestones are labeled as a release, filing, approval, or effective date. This log is updated when the desk verifies new documents. It is not automatically populated from headlines.
- 2026-11-18 · Report release
Added Georgia to the public comparison, published the first two-page research brief, and distinguished cancellation before energization from termination of an approved service contract.
- 2026-08-26 · Georgia · joint filing
Georgia Power and PSC staff filed a commitment on how Georgia Power would treat a defined shortfall after early termination of a covered contract. Source →
- November 2025 · Virginia · approved
The SCC approved Dominion’s GS-5 class. The SCC lists January 1, 2027 as its effective date. Source →
- 2025-07-23 · Ohio · effective
AEP Ohio says Schedule DCT became effective following the July 9 decision and its compliance filing. Source →
- January 2025 · Georgia · rule approved
The commission approved rules enabling longer terms and minimum bills for eligible new large loads. The September 2026 PSC fact sheet summarizes subsequent milestones. Source →