NUCLEAR ENERGY / COUNTRY EXPLAINER

UAE Nuclear Power: What Barakah Delivered

In 2013 the UAE’s first nuclear power plant was a construction project. In 2025 its four reactors supplied 39.8 TWh. Here’s what it took to get from one to the other.

WHAT WAS BUILT / WHAT WAS DELIVERED

Four reactors, brought online in stages.

Barakah, in Abu Dhabi’s Al Dhafra region, is the UAE’s first nuclear power plant. A South Korean consortium led by KEPCO won the contract in 2009 to build four APR-1400 pressurized-water reactors. Using the same reactor design across the site meant later units could draw on work done for the earlier ones, but each still needed its own licensing, testing, grid connection and transition to commercial operation.

Barakah commercial operation and reported electricity supplied
ReactorCommercial operation2025 electricity supplied (GWh)
Barakah 1April 20219,700.63
Barakah 2March 202210,098.41
Barakah 3February 20239,952.80
Barakah 4September 202410,011.67
Fleet totalFour units39,763.51

Commercial-operation months come from Emirates Water and Electricity Company. The 2025 total sums the four unit records published by the World Nuclear Association from IAEA PRIS operating data. That is electricity supplied in one calendar year, not installed power capacity or a forecast. When Unit 4 entered service, plant owner ENEC described Barakah as supplying up to a quarter of UAE electricity. That operator statement is not an independently calculated 2025 generation share.

HOW IT HAPPENED / POLICY AND INSTITUTIONS

The program started before the plant.

The UAE’s 2008 nuclear policy evaluated sources of electricity for expected demand growth. In 2009 the country established the Federal Authority for Nuclear Regulation, or FANR, and created ENEC to develop the program. The regulatory framework and the project delivery organization were separate pieces of the same effort. Read the IAEA’s UAE case study and the country nuclear power profile.

The UAE chose to rely on international fuel suppliers rather than pursue domestic uranium enrichment or reprocessing under its civil nuclear cooperation framework with the United States. The choice avoided building those domestic facilities, but it did not remove the need for reliable suppliers, safeguards, or plans for managing used fuel. Read the U.S. State Department summary of the agreement.

WHAT OTHER COUNTRIES CAN TAKE FROM IT

Copy the milestones, not the timetable.

Barakah shows why an announced reactor, a licensed reactor and a reactor delivering electricity should be counted differently. The UAE combined a repeat design, one site, an experienced international partner and a new regulator. Other countries may not be able to reproduce those conditions. The operating record alone does not tell us what another country would pay, how it would finance the plant, or how long approval and construction would take.

To judge the plant over time, watch annual electricity supplied, planned and unplanned outages, and how the grid covers demand when a unit is offline. To assess the climate effect, ask what generation Barakah actually displaced. A reactor’s annual output and its avoided emissions answer different questions.